Item Coversheet

Council Communication

Department: Public Works Admin
Case/Project No.: PW19-09
Submitted by: Matthew Cox, City EngineerĀ 
Resolution 18-135Council Action: 5/7/2018
Description

Resolution setting a public hearing for 7:00 p.m. on May 21, 2018 for the East Manawa Sewer Rehab, Phase VII.  Project # PW19-09

Background/Discussion

The area of East Manawa is very flat with open ditches.  There are no storm sewers in this area and the streets are thin asphalt or seal-coated rock roads.  During rainfall events, considerable surface ponding occurs due to the poor drainage.

 

Due to the narrow right-of-way (30 ft.) and the high water table in the area, conventional storm sewer construction is not practical.  The use of porous pavement in conjunction with a drainable granular base and shallow subdrain/conveyance system was determined to be the most cost effective means available to improve the area drainage.

 

The rehab program also includes installation of new sanitary sewers utilizing a vacuum system.

 

Phase I and II of the program have been completed and included Huron Circle from Navajo to north of Osage Street.  Phase III of the program was construction of the sanitary sewer vacuum pump station. Phase IV included the first phase of vacuum sewer installation with the porous pavement and subdrain system on Huron Circle from Navajo to just west of Blackhawk Street.  Phase V is complete and continued the rehab along Huron Circle from just west of Blackhawk Street to 585 feet east and Osage Street from Huron Circle to Victor Street. Phase VI is complete and included Blackhawk Street from Huron Circle to Victor Street and Victor Street from Osage to Blackhawk Street.

 

Phase VII is located on Blackhawk Street from Victor to Huron Circle and Aztec Street from Huron Circle to Victor.

 

This project is planned for the FY19 CIP and includes a budget of $1,000,000 in Sales Tax Funds.

 

The project schedule is as follows: Set Public Hearing May 7, 2018
Hold Public Hearing May 21, 2018
Bid Letting June 11, 2018
Award June 25, 2018
Construction Start July 1, 2018
Recommendation

Approval of this resolution.

 