Resolution setting a public hearing for June 12, 2023 at 7:00 p.m. for the Perry Road Culvert Replacement. Project # PW23-20 |
|
| | | | | | | | Background/Discussion
The Perry Road culvert is an old concrete box culvert that is in need of replacement. The existing structure has exposed rebar, spalling concrete, and missing wing walls. Replacement of the culvert is needed to maintain Perry Road and the access it provides to the properties north of the culvert.
This project was included in the FY23 CIP with a budget of $600,000 in sales tax funds for construction and engineering.
| The project schedule is as follows: |
Set Public Hearing |
May 22, 2023 |
|
Hold Public Hearing |
June 12, 2023 |
|
Bid Letting |
July 11, 2023 |
|
Award |
July 24, 2023 |
|
Construction Start |
August 2023 |
|
|
|
|
|
| | | | | | | | Recommendation
Approval of this resolution to set the public hearing for the Perry Road Culvert Replacement Project.
|
|
|