| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: PW23-10
Submitted by: Matthew Cox, Public Works Director | Resolution 23-121
ITEM 8.B. | Council Action: 4/24/2023 |
|
| | | | | | | | Description
Resolution accepting the bid of Bluffs Paving and Utility Co. Inc. for the Gifford Road Reconstruction, Phase 1. Project # PW23-10 |
|
| | | | | | | | Background/Discussion
On April 6, 2023 bids were received through the City bidding software Ion Wave as follows:
|
Division I General
|
Division II Pavement
|
Division III
Storm Sewer
|
Division IV Sanitary Sewer
|
Total
|
|
|
Bluffs Paving and Utility Co. Inc., Crescent, IA
|
$27,330.32
|
$606,166.50
|
$10,129.58
|
$1,780.11
|
$645,406.51
|
|
|
|
|
|
|
|
Carley Construction, LLC, Council Bluffs, IA
|
$33,462.50
|
$659,313.00
|
$14,820.00
|
$3,675.00
|
$711,270.50
|
|
|
|
|
|
|
|
Engineer's Opinion (Snyder)
|
$23,200.00
|
$616,518.00
|
$8,772.00
|
$2,750.00
|
$651,240.00
|
Phase 1 will reconstruct Gifford Road/S. 35th Street from Veterans Memorial Highway to 55th Avenue. The road is constructed with a thin asphalt roadway and no curbs or storm sewer. It was used as the main haul road from Veterans Memorial Highway to the south for three large levee projects along the Missouri River. The levee projects are now complete, but the road was left in poor condition. Gifford Road/S. 35th Street also provides access to the Fox Run development.
The project was included in the FY23 CIP with funding from Road Use funds.
| The project schedule is as follows: |
Award |
April 24, 2023 |
|
Construction Start |
May - August 2023 |
|
|
|
Construction is expected to be complete approximately 2 months after the start of work.
|
|
| | | | | | | | Recommendation
Approval of this resolution to award the Gifford Road Reconstruction, Phase 1 project to the low bidder.
|
|
|