| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: PW23-29
Submitted by: Matthew Cox, Public Works Director | Resolution 23-102
ITEM 8.C. | Council Action: 4/10/2023 |
|
| | | | | | | | Description
Resolution accepting the bid of Carley Construction, LLC for the 800 Block of Avenue F Reconstruction. Project # PW23-29 |
|
| | | | | | | | Background/Discussion
On March 28, 2023 bids were received through the City bidding software Ion Wave as follows:
|
Division I General
|
Division II Pavement
|
Division III Storm Sewer
|
Division IV San. Sewer
|
|
Division VI Traffic
|
Division VIII Streetscape Amenities
|
Total
|
|
Division V Water Main
|
| |
|
|
|
|
|
|
|
|
|
Carley Construction, LLC
|
$103,258.50
|
$292,776.00
|
$60,500.00
|
$100,979.00
|
$121,487.50
|
$7,325.00
|
$4,800.00
|
$691,126.00
|
|
Council Bluffs, IA
|
|
|
|
|
|
|
|
|
|
Engineer's Opinion (HGM)
|
$83,988.00
|
$227,785.00
|
$49,656.00
|
$86,726.00
|
$124,200.00
|
$4,500.00
|
$1,260.00
|
$578,115.00
|
The Council Bluffs Community School District is constructing a new Early Learning Center adjacent to Avenue F. The project includes improvements such as new sidewalks, driveway approaches and a drop off lane. The existing 800 Block of Avenue F is in poor condition and is in need of replacement to accommodate the school improvements.
A portion of the CBCSD work in the right-of-way of Avenue F required for the new Early Learning Center will be included in the City project. Having one Contractor complete the work in the right-of-way benefits both the schedule and coordination of work. The CBCSD will reimburse the City for this work.
The project was added to the FY23 CIP with funding from Local Option Sales Tax. Based on the unit prices in the bid, the Council Bluffs Community School District’s share is $84,423 per the reimbursement agreement.
| The project schedule is as follows: |
Award |
April 10, 2023 |
|
Construction Start |
May 2023 |
|
|
|
|
|
| | | | | | | | Recommendation
Approval of this resolution for the reconstruction of the 800 Block of Avenue F.
|
|
|