Resolution setting a public hearing for 7:00 p.m. on February 27, 2023 for the 800 Block of Avenue F Reconstruction. Project # PW23-29
|
|
| | | | | | | | Background/Discussion
- The Council Bluffs Community School District is constructing a new Early Learning Center adjacent to Avenue F. The project includes improvements such as new sidewalks, driveway approaches and a drop off lane. The existing 800 Block of Avenue F is in poor condition and is in need of replacement to accommodate the school improvements.
- A portion of the CBCSD work in the right-of-way of Avenue F required for the new Early Learning Center will be included in the City project. Having one Contractor complete the work in the right-of-way benefits both the schedule and coordination of work. The CBCSD will reimburse the City for this work. A reimbursement agreement between the City and the CBCSD will be forthcoming.
- The project is being added to the FY23 CIP with funding from Local Option Sales Tax. The estimated construction cost is $480,200.
- The project schedule is as follows: Set Public Hearing February 13, 2023
Hold Public Hearing February 27, 2023
Bid Letting March 28, 2023
Award April 10, 2023
Construction Start May 2023 |
|
| | | | | | | | Recommendation
Approval of this resolution to set the public hearing for the 800 Block of Avenue F Reconstruction. |
|
|