| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: PW22-16A
Submitted by: Matthew Cox, Public Works Director | Resolution 23-33
ITEM 7.H. | Council Action: 1/23/2023 |
|
| | | | | | | | Description
Resolution accepting the bid of Holder Excavating, LLC in the amount of $57,435.42 for the Steven Road West Tree Clearing. Project #PW22-16A |
|
| | | | | | | | Background/Discussion
On January 12, 2023, bids were received through the City bidding software Ion Wave as follows:
|
Division I General
|
Total
|
Holder Excavating, LLC (Altoona, IA)
|
$57,435.42
|
$57,435.42
|
J Petticord Inc. (Bondurant, IA)
|
$82,775.00
|
$82,775.00
|
Carley Construction, LLC (Council Bluffs, IA)
|
$99,625.00
|
$99,625.00
|
Kanesville Valley (D&E LLC) (Council Bluffs, IA)
|
$122,200.00
|
$122,200.00
|
Cox Contracting Company, Inc. (Council Bluffs, IA)
|
$180,017.00
|
$180,017.00
|
Valley Corporation (Valley, NE)
|
$199,533.66
|
$199,533.66
|
D&D Construction Services Inc. (Council Bluffs, IA)
|
$262,100.00
|
$262,100.00
|
Felix's Trees and Landscaping LLC (Council Bluffs, IA)
|
$410,000.00
|
$410,000.00
|
|
|
|
Engineer's Opinion
|
$62,650.00
|
$62,650.00
|
The Steven Road West project is the final project associated with the East Beltway. The project will construct a new east-west roadway from Norwood Court to State Orchard Road. The continuity for the local transportation system will support future land development, increases the capacity of existing roads to accommodate traffic demands and improves emergency access.
To remain in compliance with the Migratory Bird Treaty Act, trees cannot be removed during the period from April 1st through September 30th. If the trees are not removed over the winter, the roadway project will be delayed a year. Clearing the trees now allows for the roadway grading to begin immediately after award and most of the roadway can then be constructed in 2023. The roadway project is scheduled for a March 2023 letting.
The project will be funded with Local Option Sales Tax funds.
The project is scheduled to occur during February and March of 2023.
|
|
| | | | | | | | Recommendation
Approval of this resolution to accept the bid from Holder Excavating, LLC for the Steven Road West Tree Clearing Project.
|
|
|