Department: Public Works Admin
Case/Project No.: PW22-17
Submitted by: Matthew Cox, Public Works Director 
Resolution 23-12
ITEM 5.D.
Council Action: 1/9/2023
Description

Resolution accepting the bid of Hawkins Construction Co. for the South Expressway Reconstruction, Phase I. Project # PW22-17

Background/Discussion

On December 20, 2022 bids were received by the DOT as follows:
Hawkins Construction Co., Omaha, NE $5,860,120.66
RPL Utility, LLC, Minden, IA $6,804,947.48
Engineer’s Estimate (HDR) $5,992,869.83

The South Expressway is a major arterial roadway (formerly Iowa 192) that serves as one of the main entrances to the downtown area of Council Bluffs from I-29/I-80.  Traffic volumes are approaching 20,000 vehicles per day.  The South Expressway is currently a rural four-lane divided roadway with a depressed median.

The updated design for the reconstruction will utilize an urban typical section. The project will include new roadway pavement, drainage improvements, street lighting, and a concrete trail on the east side of the South Expressway from just north of the I-29/I-80 ramps to 23rd Avenue.

This is the first of at least two phases planned to reconstruct the South Expressway.  Phase 1 includes the area immediately north of the I-29/I-80 interchange, and continues north to just south of 19th Avenue.
This project was included in the FY22 CIP.  STBG-SWAP funds will be used for construction costs up to $4,620,000; the remaining project costs, including engineering, will be paid with Sales Tax funds. 

 

The project schedule is as follows: Construction Start         March/April 2023

 
Recommendation

Approval of this resolution to award the project to Hawkins Construction Co.

 