Background/Discussion
The Mid-America Center roof is twenty years old and several repairs have been necessary. There is concern that if sections of the roof continue to leak, it could lead to structural damage and a potential for property damage within the building.
Two roof projects have been completed to date, replacing a total area of 69,395 square feet. The Phase 2 project was completed earlier this year.
The remaining 102,625 square foot of roof will be replaced in multiple phases. Roof sections that show the most deterioration will get the highest priority. This third phase includes 50,038 square feet of roof area to be replaced.
The estimated construction cost for this project is $1,020,690. The project was included in the FY23 CIP with funding from General Fund - Gaming.
| The project schedule is as follows: |
Set Public Hearing |
November 28, 2022 |
|
Hold Public Hearing |
December 19, 2022 |
|
Bid Letting |
January 12, 2023 |
|
Award |
January 23, 2023 |
|
Construction End |
June 1, 2023 |