Background/Discussion
This project is the final segment associated with the East Beltway project.
The Steven Road West project will construct a new Steven Road segment from Norwood Drive to State Orchard Road. The continuity for the local transportation system will support future land development, increases the capacity of existing roads to accommodate traffic demands and improves emergency access.
Right-of-way authorization was approved December 13, 2021 with Resolution No. 21-353.
The following properties considered for eminent domain are:

Appraisals, review appraisals, and compensation estimates were performed for the right of way takings. Negotiations were challenging due to the impacts to trees along the corridor and the extents of temporary easement needed for fill and cut slopes due to the changing topography of the area.
In order to complete the acquisition and avoid delays to the project, eminent domain proceedings may be necessary. Negotiations are currently on-going and eminent domain will only be used if needed.