| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: PW20-11
Submitted by: Matthew Cox, Public Works Director | Resolution 22-218
ITEM 3.E. | Council Action: 9/12/2022 |
|
| | | | | | | | Description
Resolution accepting the work of Judds Bros. Construction as complete and authorizing the release of retainage after 30 days if no claims are filed in connection with the N. 28th Street Storm Sewer Rehab, Phase II. Project # PW20-11 |
|
| | | | | | | | Background/Discussion
The drainage basin limits for the N. 28th Street storm sewer are approximately I-29 to Avenue F, and N. 10th Street to N. 33rd Street. This area is roughly 580 acres. The existing storm sewer network in this area was constructed in the 1950’s and is undersized causing frequent street flooding. The existing storm sewer interceptors are located along Avenue L, North 24th Street, and Avenue K. In recent years, the unusually high ground water conditions have caused several of the storm interceptors to fail, resulting in costly emergency repairs.
Phase I is complete and included construction of a new 84” storm sewer pipe under I-29. The Phase II project included an engineering study phase to identify and prioritize future projects within the drainage basin. This work is now complete. The Phase II construction connected the existing 84” storm sewer under the interstate to the N. 28th Street storm sewer pump station.
The project was included in the FY20 CIP with funding from GO Bonds. The project budget is $1,500,000.
|
Division I General
|
Division II Pavement
|
Division III Storm Sewer
|
Division V Water Main
|
Total
|
|
|
Original Contract Amount
|
$415,300.00
|
$21,060.00
|
$1,383,164.00
|
$15,800.00
|
$1,835,324.00
|
|
Change Orders (-16.7%)
|
($39,953.50)
|
$9,833.64
|
($276,650.00)
|
$0.00
|
($306,769.86)
|
|
Final Contract Amount
|
$375,346.50
|
$30,893.64
|
$1,106,514.00
|
$15,800.00
|
$1,528,554.14
|
|
Less Previous Payments
|
$367,839.57
|
$30,275.77
|
$1,084,383.72
|
$15,484.00
|
$1,497,983.06
|
|
Retainage Due Contractor
|
$7,506.93
|
$617.87
|
$22,130.28
|
$316.00
|
$30,571.08
|
The Contractor completed the project on time and did not receive any non-compliance notices.
|
|
| | | | | | | | Recommendation
Approval of this resolution. This project will provide connection of a large storm sewer to the pump station, providing future added capacity for the N. 28th Street drainage basin.
|
|
|