Background/Discussion
Prior to this project, stormwater at the entrance to the facility flowed underneath the existing scale. This drainage was detrimental to the life of the scale foundation and other structures placed in the area.
In conjunction with the purchase and installation of a new second scale, it was necessary to improve stormwater drainage and paving at the entrance of the facility. These improvements provide adequate drainage for the scale in this phase and future phases of the project. The additional paving will provide access to the new scale ramps and approaches.
Phase two of the project is the removal of the old 1997 scale and replacement with a new outbound scale and associated paving.
These two projects will enhance safety by eliminating issues caused by crossing traffic patterns and reduce bottlenecks at the entrance of the facility.
The revised total cost of this project was $76,758.10. The project was included in the Recycling Center Operating Budget.
|
|
Total
|
|
Original Contract Amount
|
|
$76,593.00
|
|
Change Orders (0.22%)
|
|
$165.10
|
|
Final Contract Amount
|
|
$76,758.10
|
|
Less Previous Payments
|
|
$72,920.20
|
|
Retainage Due Contractor
|
|
$3,837.90
|
The Contractor completed the project on time and did not receive any non-compliance notices.