Background/Discussion
The City initiated a long term city-wide trail improvement project in 2020. The goal of the project is to upgrade those portions of the trail system either in poor or fair condition. The City Council approved $485,000 in funding within the FY23 Capital Improvement Program to improve the Lake Manawa Trail.
A bid was issued for the work on May 24, 2022 and closed on June 14, 2022 with the City receiving one bid from Old Castle Materials Midwest Co. dba Omni Engineering in the amount of $417,746.35. This amount is within the approved budget for the project.
The work is anticipated to be completed by early fall.