Item Coversheet

Council Communication

Department: Parks and Recreation
Case/Project No.: CITY WIDE TRAIL UPGRADE PROJECT, LAKE MANAWA #R23-02
Submitted by: Vincent M Martorello 
Resolution 22-177
ITEM 6.C.
Council Action: 6/27/2022
Description

Resolution to award a contract in the amount of $417,746.335 for City-Wide Trail Upgrade Project, Lake Manawa, Project #R23-02 to Old Castle Materials Midwest Co. dba Omni Engineering.
Background/Discussion

The City initiated a long term city-wide trail improvement project in 2020.  The goal of the project is to upgrade those portions of the trail system either in poor or fair condition.  The City Council approved $485,000 in funding within the FY23 Capital Improvement Program to improve the Lake Manawa Trail. 

 

A bid was issued for the work on May 24, 2022 and closed on June 14, 2022 with the City receiving one bid from Old Castle Materials Midwest Co. dba Omni Engineering in the amount of $417,746.35.  This amount is within the approved budget for the project.

 

 The work is anticipated to be completed by early fall. 

Recommendation

Approve resolution to authorized the Mayor and City Clerk to execute a contract in the amount of $417,746.335 for City-Wide Trail Upgrade Project, Lake Manawa, Project #R23-02 with Old Castle Materials Midwest Co. dba Omni Engineering.
ATTACHMENTS:
DescriptionTypeUpload Date
Resolution 22-177Resolution6/22/2022