Description

Resolution approving the plans and specifications for the Trail Ridge Street Reconstruction. Project # PW23-12

Background/Discussion

Trail Ridge Street from Grand Avenue to Mount Vernon Avenue is a residential street with infrastructure that dates back to the 1950’s and is in need of replacement. 

 

Within the project area, storm sewers are lacking, sanitary sewers are leaking, and the pavement is in poor condition. The leaking and broken sanitary sewers have caused large voids under the pavement.   

 

Reconstruction will include the addition of storm sewer, new pavement and both sanitary sewer replacement and sewer rehabilitation with a Cured-in-Place Lining (CIPP).  This is a no dig rehabilitation process where a liner is pulled through the pipe.

 

Crestwood Drive is a cul-de-sac street off Trail Ridge Street.  The Crestwood Drive sanitary sewer is in similar condition as the Trail Ridge Street sanitary sewer.  This project will receive an alternate bid for a trenchless rehabilitation of the sanitary sewer in Crestwood Drive, and the work will be included if the budget allows.  

 

The project was included in the FY23 CIP with funding from Local Option Sales Tax and Sewer Funds. The preliminary project budget is $1,525,000.

 

The project schedule is as follows: Hold Public Hearing June 27, 2022
Bid Letting July 26, 2022
Award August 8, 2022
Construction Start

September 2022

 

Recommendation

Approval of this resolution to approve the plans and specifications for the Trail Ridge Street Reconstruction Project.

 