Item Coversheet

Council Communication

Department: Public Works Admin
Case/Project No.: PW23-09
Submitted by: Matthew Cox, Public Works Director 
Resolution 22-123
ITEM 5.D.
Council Action: 5/9/2022
Description

Resolution approving the plans and specifications for the East Manawa Sewer Rehab, Phase XI. Project # PW23-09

Background/Discussion

The area of East Manawa is very flat with open ditches.  There are no storm sewers in this area and the streets are thin asphalt or seal-coated rock roads.  During rainfall events, considerable surface ponding occurs due to the poor drainage.

 

Due to the narrow right-of-way (30 ft.) and the high water table in the area, conventional storm sewer construction is not practical. The use of porous pavement in conjunction with a drainable granular base and shallow subdrain/conveyance system was determined to be the most cost effective means available to improve the area drainage.

 

The rehab program also includes installation of new sanitary sewers utilizing a vacuum system.

 

Phase I and II of the program included Huron Circle from Navajo to north of Osage Street. Phase III of the program was construction of the sanitary sewer vacuum pump station. Phase IV was the first phase of vacuum sewer installation with the porous pavement and subdrain system on Huron Circle from Navajo to just west of Blackhawk Street.  Phases V through IX continued the rehab and completed Huron Circle, Blackhawk Street, Osage Street, Victor Street, Aztec Street, East Navajo Street and extended the vacuum sewer along Navajo Street. Phase X includes Pickard Lane from Hall Walk (Alley) south to Navajo Street. Phase X is scheduled to be completed in May of 2022.

 

Phase XI includes Pickard Lane from Hall Walk (Alley) north to Navajo Street. This will complete the reconstruction on Pickard Lane.

 

This project is included in the FY23 CIP and includes a budget of $800,000 in Sales Tax Funds and $450,000 in Sewer Funds.

 

The project schedule is as follows: Hold Public Hearing May 9, 2022
Bid Letting June 2, 2022
Award June 13, 2022
Construction Start July 2022

Recommendation

Approval of this resolution. This project continues the infrastructure improvements for the neighborhood.

 