Background/Discussion
The City Council approved Phase II of the 1st Ave Trail Project in the FY 23 Capital Improvement Program. Phase I was completed in 2021 with the construction of a trail from 35th Street to 25th Street. Phase II will extend the trail from 25th Street to 16th Street and also include lighting, landscaping and site furnishings.
The bid closed on April 8, 2022 with one bid received. The bid was from Meco-Henne Contracting, Inc. in the amount of $2,778,905.70. Meco-Henne was the general contractor for Phase I.
The construction timeframe is expected to be from May through October.