Item Coversheet

Council Communication

Department: Parks and Recreation
Case/Project No.: 1st Avenue Trail Phase II, Project # CD23-01
Submitted by: Vincent M Martorello 
Resolution 22-115
ITEM 5.D.
Council Action: 4/25/2022
Description

Resolution awarding the contract for the 1st Ave Trail Project Phase II to Meco-Henne Contracting, Inc. 

Background/Discussion

The City Council approved Phase II of the 1st Ave Trail Project in the FY 23 Capital Improvement Program.  Phase I was completed in 2021 with the construction of a trail from 35th Street to 25th Street.  Phase II will extend the trail from 25th Street to 16th Street and also include lighting, landscaping and site furnishings. 

 

The bid closed on April 8, 2022 with one bid received.  The bid was from Meco-Henne Contracting, Inc. in the amount of $2,778,905.70.  Meco-Henne was the general contractor for Phase I. 

 

The construction timeframe is expected to be from May through October. 

Recommendation

Approve the resolution authorizing the Mayor and City Clerk to execute a contract with Meco-Henne Contracting, Inc.in the amount of $2,778,905.70 for the 1st Avenue Trail, Project # CD23-01. 
ATTACHMENTS:
DescriptionTypeUpload Date
Resolution 22-115Resolution4/19/2022