Background/Discussion
The Council approved the First Avenue Program Project Phase II with a budget of $2,800,000.00. Phase II includes the construction of the First Avenue Trail from 25th Street to 16th Street. The project also includes trail amenities such as lighting, landscaping, site furnishings, and signage.
Phase I of the trail construction project was substantially complete in late November 2021. The completed trail extends from 35th Street to 25th Street. Once Phase II of the trail is completed, the city will have connectivity from downtown to the riverfront.