Item Coversheet

Council Communication

Department: Public Works Admin
Case/Project No.: PW20-11
Submitted by: Matthew Cox, Public Works Director 
Resolution 21-324
ITEM 6.I.
Council Action: 11/8/2021
Description

Resolution accepting the bid of Judds Bros. Construction Co. for the N. 28th Street Storm Sewer Rehab, Phase II.  Project # PW20-11

Background/Discussion

On October 26, 2021 bids were received through the City bidding software Ion Wave as follows:

 

Division I General

Division II Pavement

Division III Storm Sewer

Division V Water Main

Total

 

Judds Bros. Construction Co.     

 

  $415,300.00  

 

  $21,060.00  

 

  $1,383,164.00  

 

  $15,800.00  

 

  $1,835,324.00

Lincoln, NE

 

Peterson Contractors, Inc.

$613,103.00

$29,600.00

$1,191,266.00

$25,000.00

  $1,858,969.00

Reinbeck, IA

 

Valley Corporation

$883,916.01

$33,667.82

$1,626,602.23

$44,353.01

  $2,588,539.07

Valley, NE

 

Engineer's Opinion (HGM)

$286,215.00

$21,740.00

  $959,819.00

$10,000.00

  $1,277,774.00

 

The drainage basin limits for the N. 28th Street storm sewer are approximately I-29 to Avenue F, and N. 10th Street to N. 33rd Street.  This area is roughly 580 acres.  The existing storm sewer network in this area was constructed in the 1950’s and is undersized causing frequent street flooding. The existing storm sewer interceptors are located along Avenue L, North 24th Street, and Avenue K.  In recent years, the unusually high ground water conditions have caused several of the storm interceptors to fail, resulting in costly emergency repairs.

 

Phase I is complete and included construction of a new 84” storm sewer pipe under I-29. The Phase II project included an engineering study phase to identify and prioritize future projects within the drainage basin.  This work is now complete.  Phase II construction will connect the existing 84” storm sewer under the interstate to the N. 28th Street storm sewer pump station. 

 

The project was included in the FY20 CIP with $1,500,000 in GO Bond funding.  There are $209,236 in unused GO Bonds that can be applied to the project budget from PW20-09, E. Manawa Sewer Rehab, Phase VIII.  The balance of the project costs will be paid with local option sales tax funds.

 

The project is scheduled for a construction start in December 2021.

 

Recommendation

Approval of this resolution. This project will provide connection of a large storm sewer to the pump station, providing future added capacity for the N. 28th Street drainage basin.

 

ATTACHMENTS:
DescriptionTypeUpload Date
Resolution 21-324Resolution11/3/2021