Item Coversheet

Council Communication

Department: Public Works Admin
Case/Project No.: PW20-11
Submitted by: Matthew Cox, Public Works Director 
Resolution 21-281
ITEM 5.A.
Council Action: 9/27/2021
Description

Resolution approving the plans and specifications for the N. 28th Street Storm Sewer Rehab, Phase II.  Project # PW20-11

Background/Discussion

The drainage basin limits for the N. 28th Street storm sewer are approximately I-29 to Avenue F, and N. 10th Street to N. 33rd Street.  This area is roughly 580 acres.  The existing storm sewer network in this area was constructed in the 1950’s and is undersized causing frequent street flooding. The existing storm sewer interceptors are located along Avenue L, North 24th Street, and Avenue K.  In recent years, the unusually high ground water conditions have caused several of the storm interceptors to fail, resulting in costly emergency repairs.

 

Phase I is complete and included construction of a new 84” storm sewer pipe under I-29. The Phase II project included an engineering study phase to identify and prioritize future projects within the drainage basin.  This work is now complete.  Phase II construction will connect the existing 84” storm sewer under the interstate to the N. 28th Street storm sewer pump station. 

 

The project was included in the FY20 CIP with funding from GO Bonds.  The project budget is $1,500,000. 

 

The project schedule is as follows: Hold Public Hearing September 27, 2021
Bid Letting October 26, 2021
Award November 9, 2021
Construction Start December 2021
Recommendation

Approval of this resolution. This project will provide connection of a large storm sewer to the pump station, providing future added capacity for the N. 28th Street drainage basin.

 

ATTACHMENTS:
DescriptionTypeUpload Date
MapMap9/17/2021
Resolution 21-281Resolution9/22/2021