| | | | | | | | Description
Resolution accepting the bid of Black Hawk Roof Company in the amount of $531,600.00 for the Mid-America Center Roof Replacement Project, Phase 2. Project # BM22-02 |
|
| | | | | | | | Background/Discussion
On September 14, 2021, five bids were received through the City bidding software, Ion Wave, as follows:
|
|
Total
|
|
Black Hawk Roof Company, Cedar Falls, IA
|
$531,600.00
|
|
Drey Roofing (Drey Incorporated), Omaha, NE
|
$548,900.00
|
|
White Hawk Roofing and Construction LLC, Omaha, NE
|
$567,352.00
|
|
10 Men Roofing, Omaha, NE
|
$595,000.00
|
|
Stag Roofing LLC, Omaha, NE
|
$597,000.00
|
|
Engineer’s Estimate (HGM)
|
$569,019.00
|
The Mid-America Center roof is approaching twenty years old. There have been several repairs made in recent years. There is concern that if the roof continues to leak, there could be structural damage and a potential for property damage within the building.
Mid-America Center Roof Replacement Project, Phase 1 was a 31,245 square feet project and was just recently completed.
The remaining 140,775 square foot roof will be replaced in several phases. Roof sections that show the most deterioration will get the highest priority. This second phase includes 38,150 square feet of roof area to be replaced.
The total cost of this project is $560,600.00 including $29,000.00 for professional services provided by HGM. The project was included in the FY22 CIP with funding from GO bonds.
The project is scheduled to be complete by June 1, 2022.
|
|
| | | | | | | | Recommendation
Approval to accept the bid of Black Hawk Roof Company in the amount of $531,600.00. This phase of the project will replace the most deteriorated portions of the roof to reduce the potential for damage.
|
|
|