| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: BM-22-02
Submitted by: Jeremy Noel, Public Works Operations ManagerĀ | Resolution 21-229
ITEM 3.C. | Council Action: 8/9/2021 |
|
| | | | | | | | Description
Resolution setting a public hearing for 7:00 p.m. on August 23, 2021, for the Mid-America Center Roof Replacement Project, Phase 2. Project # BM-22-02 |
|
| | | | | | | | Background/Discussion
The Mid-America Center roof is approaching twenty years old. There have been several repairs made in recent years. There is concern that if the roof continues to leak, there could be structural damage and a potential for property damage within the building. Mid-America Center Roof Replacement Project, Phase 1 was a 31,245 square feet project and was just recently completed.
The remaining 140,775 square foot roof will be replaced in several phases. Roof sections that show the most deterioration will get the highest priority. This second phase includes 38,150 square feet of roof area to be replaced.
The estimated construction cost for this project is $568,640. The project was included in the FY22 CIP with funding from GO bonds.
The project schedule is as follows: |
Set Public Hearing |
August 9, 2021 |
|
Hold Public Hearing |
August 23, 2021 |
|
Bid Letting |
September 14, 2021 |
|
Award |
September 27, 2021 |
|
Construction End |
June 1, 2022 |
|
|
| | | | | | | | Recommendation
Approval of this resolution. This phase of the project will replace the most deteriorated portions of the roof to reduce the potential for damage.
|
|
|