Resolution accepting the bid of Visu Sewer Inc. in the amount of $686,946 for the Mosquito Creek Sanitary Sewer Rehab. Project # PW21-15 |
|
| | | | | | | | Background/Discussion
On July 27, 2021 bids were received through the City bidding software Ion Wave as follows:
|
Division I General
|
Division II Pavement
|
Total
|
|
Visu Sewer Inc., Pewaukee, WI
|
$286,112.00
|
$400,834.00
|
$686,946.00
|
|
|
|
|
SAK Construction, LLC, O'Fallon, MO
|
$383,640.00
|
$583,338.00
|
$966,978.00
|
|
|
|
|
Municipal Pipe and Tool Co. LLC, Hudson, IA
|
$462,134.40
|
$797,309.00
|
$1,259,443.40
|
|
|
|
|
Engineer's Opinion (HGM)
|
$331,700.00
|
$529,200.00
|
$860,900.00
|
The Mosquito Creek sanitary sewer is a major trunk sewer that serves the east side of the City.
Two locations are in need of pipe rehabilitation. One location is just south of the intersection of Madison Ave. and Valley View Drive. This sewer is located along the bank of the creek and has developed cracks/holes from corrosion that are in need of repair. Due to the location of the pipe near the creek, accessibility is difficult. The method of rehabilitation will be Cured-in-Place Pipe Lining (CIPP). This is a no dig rehabilitation process where a liner is pulled through the pipe.
The second sanitary sewer rehabilitation is along Mosquito Creek just north of East South Omaha Bridge Road. As part of the railroad consolidation that took place in 2016\2017 for the Council Bluffs Interstate Improvements, the BNSF railroad relocated their tracks adjacent to the sewer and under the new I-29 Bridges. The sewer was identified to be lined with CIPP once the railroad construction was complete. The City entered into agreement U-2014-16035 with the Iowa DOT for reimbursement to line the pipe.
This project was included in the FY21 CIP with a budget of $865,000. The Iowa DOT reimbursement amount is $373,250.
The project schedule is as follows: Construction Start October\November 2021
|
|
| | | | | | | | Recommendation
Approval of this resolution to award the project to Visu Sewer Inc. The rehabilitation project will make repairs to an essential trunk sewer within the City’s sanitary sewer collection system.
|
|
|