Item Coversheet

Council Communication

Department: Public Works Admin
Case/Project No.: PW22-23
Submitted by: Matthew Cox, Public Works Director 
Resolution 21-235
ITEM 4.A.
Council Action: 8/9/2021
Description

Resolution approving the plans and specifications for the 2100 Block of Avenue H Sanitary Sewer Rehabilitation.  Project #PW22-23

Background/Discussion

The sanitary sewer in the 2100 Block of Avenue H and the sewer in N. 22nd Street from the alley to Avenue H is a reinforced concrete pipe constructed over 60 years ago.

 

During a recent lateral connection repair, it was discovered that the sanitary sewer main was in very poor condition.  The reinforced concrete pipe has disintegrated to the extent that in some locations the pipe is non-existent.  The sewer replacement will require the removal and replacement of the street pavement.

 

This project requires immediate attention and is being added to the FY22 CIP with costs to be paid with Sales Tax Funds. The estimated construction cost is $640,000.

 

The project schedule is as follows: Hold Public Hearing August 9, 2021
Bid Letting September 2, 2021
Award September 13, 2021
Construction Start September\October 2021

Recommendation

Approval of this resolution. This project completes necessary sewer repairs along Avenue H and N. 22nd Street.

 