Item Coversheet

Council Communication

Department: Public Works Admin
Case/Project No.: CD21-01
Submitted by: Matthew Cox, Public Works Director 
Resolution 21-91
ITEM 5.B.
Council Action: 3/22/2021
Description

Resolution approving the plans and specifications for the Lake Manawa Power Center Entrance Enhancement.  Project # CD21-01

Background/Discussion

The Lake Manawa Power Center is a large development with several retail and restaurant destinations near I-80/I-29.  32nd Avenue is one of two main entrances into the shopping center and there is a desire to update the entrance.

 

As part of the Council Bluffs Interstate and Railroad Consolidation projects, the railroad tracks that were located between the South Expressway and Power Center have been removed and relocated.  The elimination of the tracks will allow the street to be lowered resulting in an improved street profile. 

 

The project will reconstruct 225 feet of 32nd Avenue from the South Expressway to the east. The project will also construct a sidewalk on the south side of 32nd Ave. from the South Expressway to Manawa Centre Drive and along the west side of Manawa Centre Drive from 32nd Avenue to the existing bus stop just north of the Menard’s driveway.  Trail stub outs north and south of 32nd Avenue will be constructed for future trail expansion along the South Expressway.  The traffic signal at 32nd Avenue will be modified to provide a north-south pedestrian crossing on the east side of the South Expressway.

 

The estimated construction cost for the project is $592,280. The estimated costs for the SSMID portion which includes sidewalk, trail, and traffic signal modifications for pedestrian movements is $81,290.

 

This project was included in the FY21 CIP and includes a budget of $300,000 in Sales Tax funds, $150,000 in GO Bond funds, and $275,000 in SSMID funding.

 

The project schedule is as follows: Hold Public Hearing March 22, 2021
Letting April 13, 2021
Award April 26, 2021
Construction Start May/June 2021
Recommendation

Approval of this resolution.  This project will improve the street profile by removing the existing railroad crossing along 32nd Ave. and provide additional sidewalk for the Lake Manawa Power Center.

 

ATTACHMENTS:
DescriptionTypeUpload Date
Resolution 21-91Resolution3/17/2021