| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: PW21-06C
Submitted by: Matthew Cox, Public Works Director | Resolution 21-76
ITEM 3.E. | Council Action: 3/8/2021 |
|
| | | | | | | | Description
Resolution accepting the bid of Peterson Contractors, Inc. in the amount of $6,378.117.40 for the Levee Certification Project, Geotechnical MR_3 and MR_4. Project # PW21-06C |
|
| | | | | | | | Background/Discussion
On February 23, 2021, bids were received through the City bidding software, Ion Wave, as follows:
|
MR_3 and
MR_4
Base Bid
|
MR_3
Division I General
|
MR_3
Division II Pavement
|
MR_3
Division
VIII
Misc.
|
MR_4
Division I
General
|
MR_4
Division II
Pavement
|
MR_4
Division III
Storm Sewer
|
MR_4
Division VIII
Misc.
|
Total
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Peterson Contractors, Inc.,
Reinbeck, IA
|
$175,505.00
|
$955,560.75
|
$59,948.15
|
$288,405.00
|
$4,457,403.50
|
$104,950.00
|
$329,790.00
|
$6,555.00
|
$6,378,117.40
|
|
|
|
|
|
|
|
|
|
|
|
Valley Corporation,
Valley, NE
|
$360,835.28
|
$1,338.881.29
|
$52,985.88
|
$74,728.48
|
$5,604,235.54
|
$117,015.01
|
$199,759.79
|
$5,137.05
|
$7,753,578.32
|
|
|
|
|
|
|
|
|
|
|
|
Engineer’s Opinion (HDR)
|
$424,000.00
|
$1,418,405.85
|
$81,490.00
|
$59,800.00
|
$6,855,505.20
|
$90,925.00
|
$151,172.50
|
$1,725.00
|
$9,083,023.55
|
In order to meet the criteria for levee certification, improvements to each of the levee systems will be necessary.
The purpose of the Geotechnical MR_3 and MR_4 projects are to resolve levee seepage and stability deficiencies. The project will construct large berms along the land side of the levee.
Public Works was successful is securing funding through the Economic Development Authority (EDA) Economic Adjustment Assistance disaster recovery program. The estimated cost for construction is $6,378,117.40. The EDA share is 80% of construction costs with a maximum contribution of $8,485,749. The City’s share will be funded by funds from the Iowa Flood Mitigation Program and Sales Tax Funds programmed for levee improvements.
Construction is scheduled to start in April 2021 and be complete by June 2022.
|
|
| | | | | | | | Recommendation
Approval of this resolution. This project will improve the levee system to meet the criteria for certification.
|
|
|