Description

Resolution setting a public hearing for February 8, 2021 at 7:00 p.m., for the Mid-America Center Roof Replacement Project, Phase I.  Project # BM21-02

Background/Discussion

The Mid-America Center roof is approaching twenty years old.  There have been several repairs made in recent years. There is concern that if the roof continues to leak, there could be structural damage and a potential for property damage within the building.

 

The 172,020 square foot roof will be replaced in several phases.  Roof sections that show the most deterioration will get the highest priority.  This first phase includes 31,245 square feet of roof area to be replaced. 

 

The estimated construction cost for this project is $455,400.  The project was included in the FY21 CIP with funding from the General Fund.

 

The project schedule is as follows: Set Public Hearing January 25, 2021
Hold Public Hearing February 8, 2021
Letting February 25, 2021
Award March 8, 2021
Construction End June 18, 2021

Recommendation

Approval of this resolution. This phase of the project will replace the most deteriorated portions of the roof to reduce the potential for damage.

 

ATTACHMENTS:
DescriptionTypeUpload Date
Notice of Public HearingOther1/15/2021
Resolution 21-19Resolution1/20/2021