Item Coversheet

Council Communication

Department: Public Works Admin
Case/Project No.: PW21-13
Submitted by: Matthew Cox, Public Works Director 
Resolution 20-263
ITEM 3.C.
Council Action: 11/9/2020
Description

Resolution setting a public hearing November 23, 2020 at 7:00 p.m. for right-of-way authorization in connection with the North Broadway Bridge over Indian Creek.  Project #PW21-13

Background/Discussion

The Competitive Highway Bridge Program (CHBP) funding was made available by Division L of the Consolidated Appropriations Act of 2018 by the federal government.  The North Broadway Bridge over Indian Creek was selected to receive the CHBP funds.  

 

The North Broadway Bridge over Indian Creek (FHWA Structure 043960) ranked high enough among other bridges in the state to qualify for participation in the program.

 

The CHBP funds allow for funding of 55% of the construction cost of the bridge up to a maximum of $1,256,260.    The remaining construction costs will be paid using Federal-Aid SWAP funds per agreement No. 4-19-HBP-SWAP-10.  The preliminary estimate for the project is $2,300,000.

 

The existing bridge will be replaced with a box culvert section along Indian Creek.  A new three-lane roadway with a trail on the east side and sidewalk on the west side will be constructed over the box culvert.  To accommodate this roadway section with trail and sidewalk will require property acquisitions and temporary easements adjacent to North Broadway.

 

The engineering and right-of-way acquisition costs associated with the project will be paid by the City.

 

Recommendation

Approval of this resolution.

 