Background/Discussion
The Community Development Department moved to City Hall in March of 2020. The Fire Department’s Administrative Staff along with the Fire Marshall’s Office moved into the former Community Development Department’s space which is not ADA accessible.
This project will provide a corridor that begins at the front entrance of the Central Fire Station on the east side of the building. This hallway will pass through the building and open into the new Fire Administration offices thus eliminating the ADA accessibility issues.
The estimated cost of this project is $72,565. The project was included in the FY21 CIP with funding from the General Fund.
| The project schedule is as follows: |
Hold Public Hearing |
October 26, 2020 |
|
Bid Letting |
November 17, 2020 |
|
Award |
December 14, 2020 |
|
Construction End |
March 31, 2021 |