Background/Discussion
The Community Development Department relocated to the space once occupied by the Health Department at City Hall. This space had not been renovated for decades and was not ADA accessible. The remodel has given this space a fresh new look. It provides adequate office space for the Community Development staff and a ramp system was installed to address ADA requirements. The relocation of the Community Development Department has enhanced communication and coordination with other City departments.
The Fire Department’s administrative staff was in desperate need of more office space. To remedy that issue, they have moved into the area previously occupied by Community Development.
This project was paid for using Gaming funds.
|
Total
|
|
Original Contract Amount
|
$158,844.00
|
|
Change Orders (-6.96%)
|
($11,048.56)
|
|
Final Contract Amount
|
$147,795.44
|
|
Less Previous Payments
|
$139,853.24
|
|
Retainage Due Contractor
|
$7,942.20
|
The Contractor did not complete the project on time. Liquidated damages in the amount of $18,500.00 were assessed.