Item Coversheet

Council Communication

Department: Public Works Admin
Case/Project No.: FY15-06C
Submitted by: Matthew Cox, Public Works Director 
Resolution 20-186
ITEM 3.D.
Council Action: 8/10/2020
Description

Resolution accepting the work of Valley Corporation, Inc. as complete and authorizing release of retainage after 30 days if no claims are filed in connection with the Levee Certification Project, Geotechnical MR_5.  Project #FY15-06C

Background/Discussion

The City of Council Bluffs owns or sponsors multiple levee segments which encompass the City Federal Levee System, providing flood protection from the Missouri River, Mosquito Creek, and Indian Creek.  These levee systems are currently shown on FEMA floodplain maps as being accredited and are identified as providing protection from the 100-year flood or 1% annual chance flood event.

 

In order to maintain the level of protection identified on the FEMA Flood Insurance Rate Map, it is necessary to provide documentation to FEMA that complies with the requirements of 44 CFR 65.10. If the levees are not certified, they will be de-accredited and FEMA will begin the process of updating maps.  Areas previously protected by the levees will be identified as flood-prone.

 

In order to meet the criteria for levee certification, improvements to each of the levee systems will be necessary.  The purpose of the Geotechnical MR_5 project was to resolve seepage deficiencies along the Missouri River levee by constructing a seepage and stability berm.  The project also incorporated the correction of any noted deficiencies from the latest USACE inspection.

 

Each year of the FY14 thru FY19 CIP budgets have included a programmed amount in Local Option Sales Tax funds for levee improvements.  In addition to LOST funds, the City is able to capture a portion of the State sales tax revenues through the Iowa Flood Mitigation Program.  Through this program, the City is eligible to receive $57 M over a 20-year period. 

 

Division I

General

 

Total

Original Contract Amount

$1,260,321.67

$1,260,321.67

Change Orders (-14.8%)

($187,026.59)

($187,026.59)

Final Contract Amount

$1,073,295.08

$1,073,295.08

Less Previous Payments

$1,019,630.32

$1,019,630.32

Retainage Due Contractor

$     53,664.76

$     53,664.76

 

The Contractor completed the project on time and did not receive any non-compliance notices.

 

Recommendation

Approval of this resolution. 

 