Item Coversheet

Council Communication

Department: Public Works Admin
Case/Project No.: PW21-09
Submitted by: Matthew Cox, Public Works Director 
Resolution 20-131
ITEM 7.B.
Council Action: 5/18/2020
Description

Resolution accepting the bid of Compass Utility, LLC for the East Manawa Sewer Rehab, Phase IX. Project # PW21-09     

Background/Discussion

On May 7, 2020 bids were received in the office of the city clerk as follows:

Division I General

Division II Pavement

Division III Storm Sewer

Division IV San. Sewer

Division V Water Main

Total

Compass Utility, LLC, Council Bluffs, IA

$149,344.93

$226,900.81

$34,341.70

$362,699.67

$94,707.39

$867,994.50

Carley Construction, LLC, Council Bluffs, IA

$356,020.00

$293,521.00

$42,451.00

$543,705.00

$117,875.00

$1,353,572.00

Engineer's Opinion (EGA)

$203,015.00

$222,208.00

$30,077.75

$387,062.00

$98,570.00

$940,932.75

 

The area of East Manawa is very flat with open ditches.  There are no storm sewers in this area and the streets are thin asphalt or seal-coated rock roads.  During rainfall events, considerable surface ponding occurs due to the poor drainage.  Due to the narrow right-of-way (30 ft.) and the high water table in the area, conventional storm sewer construction is not practical.  The use of porous pavement in conjunction with a drainable granular base and shallow subdrain/conveyance system was determined to be the most cost effective means available to improve the area drainage.  The rehab program also includes installation of new sanitary sewers utilizing a vacuum system.

 

Phase I and II of the program included Huron Circle from Navajo to north of Osage Street.  Phase III of the program was construction of the sanitary sewer vacuum pump station. Phase IV was the first phase of vacuum sewer installation with the porous pavement and subdrain system on Huron Circle from Navajo to just west of Blackhawk Street.  Phase V continued the rehab along Huron Circle from just west of Blackhawk Street to 585 feet east and Osage Street from Huron Circle to Victor Street. Phases VI and VII are now complete and included Blackhawk Street, Victor Street from Osage to Blackhawk Street, and Aztec Street from Huron Circle to Victor. Phase VIII is substantially complete and includes Victor Street and Aztec Street from Victor to the south.

 

Phase IX includes extending the vacuum sewer along the west side of Navajo Street from just south of Huron Circle to south of Victor Street and reconstruction of East Navajo Street from Victor Street to Huron Circle.

 

This project was included in the FY21 CIP and includes a budget of $1,000,000 in Sales Tax Funds.

 

The project schedule is as follows: Award May 18, 2020
Construction Start June 2020

Recommendation

Approval of this resolution. 

 