Item Coversheet

Council Communication

Department: Public Works Admin
Case/Project No.: PW20-15
Submitted by: Matthew Cox, Public Works Director 
Resolution 20-116
ITEM 4.B.
Council Action: 5/4/2020
Description

Resolution approving the plans and specifications for the Oakland Drive Rehabilitation. Project # PW20-15

Background/Discussion

Oakland Drive is a narrow roadway with a steep grade and tight switchback curve which connects Military Avenue to Oak Park Road and Oakland Avenue.  It is the only roadway that provides access for residents along Oak Park Road.  Oakland Drive has no storm sewers and the pavement is in poor condition.  The existing sanitary sewer is clay pipe from the 1950’s and needs to be replaced.

 

The project will include reconstruction of Oakland Drive from Military Avenue to Lafayette Avenue and Lafayette Avenue from Oakland Drive to Oakland Avenue.  Reconstruction will include new pavement, storm sewer, sanitary sewer, and water main. The storm sewer from Military Avenue, north of Avenue G, to Curtis Street will be reconstructed to increase the capacity of the storm sewer.  The storm sewer is the collector line for Oakland Drive and is currently under sized and surcharges during rain events. 

 

The project was included in the FY20 CIP with funding from Local Option Sales Tax and Road Use Funds.  The total project budget is $1,500,000.

 

The project schedule is as follows: Hold Public Hearing May 4, 2020
Bid Letting May 19, 2020
Award June 8, 2020
Construction Start June/July 2020

Recommendation

Approval of this resolution.

 

ATTACHMENTS:
DescriptionTypeUpload Date
MapMap4/24/2020
Resolution 20-116Resolution4/29/2020