Case/Project No.: PW20-14
Submitted by: Matthew Cox, Public Works Director 
Resolution 20-66
ITEM 6.J.
Council Action: 2/24/2020
Description

Resolution accepting the bid of Judds Bros. Construction Co. in the amount of $297,500.00 for the 6th Avenue Pump Station Trash Rack Rehab.  Project #PW20-14

Background/Discussion

On February 13, 2020, bids were received in the office of the city clerk as follows:

 

Judds Brothers Construction Co., Lincoln, NE

$297,500.00

Eriksen Construction Co., Inc., Blair, NE

$394,000.00

All Purpose Construction, LaVista, NE

$444,300.00

Engineer’s Estimate (Snyder & Associates)

$484,700.00

                       

The 6th Avenue sanitary sewer pump station is the third largest station in the sanitary collection system with nearly 35% of the City’s sewage passing through this station. 

 

The wastewater entering the pump station is screened for solids and debris. This removal process protects the pumps from clogging and limits the potential for damage. Larger stations, like 6th Avenue, utilize a mechanically operated trash rack to clean the screens.  

 

The pump station still has the original bar screen units constructed in 1992. This project will replace the trash rack system which has reached its service life limit. The newer technology of a modern trash rack will provide reliable removal, handling, storage, and disposal of the screenings.

 

The project will include the necessary modifications to the screenings room and electrical controls to accommodate the new system.

 

Supervisory and process control panels modified in 1992, with portions dating back to the early 1980’s, will be removed and replaced.

 

This project is included in the FY20 CIP and includes a budget of $600,000 in sales tax funds.

 

The project is scheduled to be complete by December 2020.

   

Recommendation

Approval of this resolution.

 