| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: PW20-20
Submitted by: Matthew Cox, Public Works Director | Resolution 20-40
ITEM 6.E. | Council Action: 2/10/2020 |
|
| | | | | | | | Description
Resolution accepting the bid of Hawkins Construction Company in the amount of $9,169,804.88 for the West Broadway Reconstruction, Segment 4. Project # PW20-20 |
|
| | | | | | | | Background/Discussion
On January 23, 2020, one bid was received in the office of the city clerk as follows:
|
Division I General
|
Division II Pavement
|
Division III Storm Sewer
|
Division IV Sanitary Sewer
|
Division V Water Main
|
Division VI Traffic Signals
|
Division VIII Lighting
|
Division IX Streetscape Amenities
|
Total
|
|
|
Hawkins Construction Co.
|
$1,186,443.50
|
$4,631,505.14
|
$694,666.38
|
$157,168.10
|
$98,629.97
|
$665,178.52
|
$483,396.10
|
$1,252,817.18
|
$9,169,804.88
|
|
Omaha, NE
|
|
|
|
|
|
|
|
|
|
|
Engineer's Opinion (HGM)
|
$1,084,418.00
|
$4,195,872.60
|
$703,403.00
|
$151,300.00
|
$100,000.00
|
$617,205.50
|
$469,730.00
|
$1,250,011.00
|
$8,571,940.10
|
The Contract Documents for the project include a special provision for incentives and disincentives. If the maximum incentive of $120,000 is earned by Hawkins, the project cost will be $9,289,804.88. Approval of the resolution accepting the bid includes authorization for this incentive payment.
Segment 4 of the reconstruction project will completely rebuild West Broadway from just west of 24th Street to just west of 19th Street including the replacement of pavement, traffic signals, street lights, sidewalks, and storm sewers with drainage improvements. The project also includes streetscape amenities such as decorative pedestrian lights, brick paver bands behind the curbs and at intersections, ornamental fencing, ornamental arms for street lights, concrete pavers in crosswalks, decorative paving in the center turn lane and at key intersections, neighborhood masonry columns, and trees.
As a condition of the Transfer of Jurisdiction, Iowa DOT has provided $20 million in funding for assuming ownership of the roadway previously identified as US-6. This project was included in the FY20 CIP and has a revised budget of $6,500,000 in IDOT funding, $1,000,000 from GO Bonds, and the balance in Sales Tax Funds. The Iowa West Foundation has agreed to provide funding for the streetscape amenities which are estimated to be $1,352,590.
| The project schedule is as follows: |
Award |
February 10, 2020 |
|
Construction Start |
March\April 2020 (weather dependent) |
|
Substantial Completion |
December 2020 |
|
|
|
|
|
| | | | | | | | Recommendation
Approval of this resolution.
|
|
|