Background/Discussion
Thousands of people have attended events at the Mid-America Center since it opened its doors to the public in October of 2002. Due to the high volume of usage and wear over the years, the fixtures in these rooms now need to be replaced. This project will renovate the Exhibit Hall Pre-Function Restrooms, the Ballroom Pre-Function Restrooms and the Restrooms that serve Hallways H, I, and J.
The renovation will include removal and replacement of the dated metal toilet partitions with solid HDPE (high density polyethylene) partitions which will never rust or need painted. New solid surface countertops, sinks, and hands-free faucets will be installed. The lighting with be upgraded with new high efficiency LED lights. The rooms will have the wallpaper removed and the walls will be painted.
Renovating these areas will provide a greater overall customer experience and enhance the competitive advantage across this market.
The estimated cost for the base renovation is $195,745, and with all alternatives included the total project is $218,040. This project was included in the CIP and is identified as BM20-02. Funding is from the General Fund.
| The project schedule is as follows: |
Set Public Hearing |
February 10, 2020 |
|
Hold Public Hearing |
February 24, 2020 |
|
Letting |
March 10, 2020 |
|
Award |
March 23, 2020 |
|
Construction End |
June 25, 2020 |
|
|
|