Item Coversheet

Council Communication

Department: City Clerk
Case/Project No.:
Submitted by: Matthew Cox, Public Works Director 
Resolution 20-09
ITEM 5.D.
Council Action: 1/13/2020
Description

Resolution approving the Plans, Specifications, Form of Contract and Cost Estimate for the 6th Avenue Pump Station Trash Rack Rehab Project #PW20-14
Background/Discussion

• The 6th Avenue sanitary sewer pump station is the third largest station in the sanitary collection system with nearly 35% of the City’s sewage passing through this station.  


• The wastewater entering the pump station is screened for solids and debris. This removal process protects the pumps from clogging and limits the potential for damage. Larger stations, like 6th Avenue, utilize a mechanically operated trash rack to clean the screens.   


• The pump station still has the original bar screen units constructed in 1992. This project will replace the trash rack system which has reached its service life limit. The newer technology of a modern trash rack will provide reliable removal, handling, storage, and disposal of the screenings. 


• The project will include the necessary modifications to the screenings room and electrical controls to accommodate the new system.


• Supervisory and process control panels modified in 1992, with portions dating back to the early 1980’s, will be removed and replaced.


• This project is included in the FY20 CIP and includes a budget of $600,000 in sales tax funds.


• The project schedule is as follows:

Hold Public Hearing January 13, 2020
Bid Letting February 13, 2020
Award February 24, 2020
Construction Start March 16, 2020

Recommendation

Approval
ATTACHMENTS:
DescriptionTypeUpload Date
Resolution 20-09Resolution1/8/2020