Item Coversheet

Council Communication

Department: Public Works Admin
Case/Project No.: B-19-90
Submitted by: Pat Miller, Public Works Operations Director 
Resolution 19-154
ITEM 4.D.
Council Action: 6/24/2019
Description

Resolution approving the plans, specifications, form of contract, and cost estimate for the Community Development Renovation Project.

Background/Discussion

The Community Development Department will be moving into the space once occupied by the Health Department at City Hall. This space has not been renovated for decades and is currently not ADA accessible. The remodel will give this space a fresh new look.  It will provide adequate office space for the Community Development staff and will address the ADA issue with a ramp system that will be installed as part of this project.  This move will enhance communication and availability of the Community Development Department with other City departments. 

 

The Fire Department’s administrative staff is in desperate need of more office space.  They will move into the area Community Development currently occupies to remedy that issue.

 

The estimated cost of this project is $184,000.  Funding for this project will be paid for by the Gaming Fund.

 

The project schedule is as follows: Hold Public Hearing June 24, 2019
Bid Letting July 23, 2019
Award August 12, 2019
Construction End November 27, 2019
Recommendation

Approval of this resolution. 

 