Item Coversheet

Council Communication

Department: Public Works Admin
Case/Project No.: PW 19-20
Submitted by: Matthew Cox, City EngineerĀ 
Resolution 19-72
ITEM 7.A.
Council Action: 3/11/2019
Description

Resolution accepting the bid of Hawkins Construction Company in the amount of $8,017,377.95 for the West Broadway Reconstruction, Segment 3. Project # PW19-20

Background/Discussion

On February 26, 2019, one bid was received in the office of the city clerk as follows:

Division I General

Division II Pavement

Division III Storm Sewer

Division IV Sanitary Sewer

Division V Water Main

Division VI Traffic Signals

Division VIII Lighting

Division IX Streetscape Amenities

Total

Hawkins Construction Co.

$944,526.85

$3,528,894.09

$681,060.99

$63,887.80

$84,905.17

$809,595.57

$438,116.51

$1,466,390.97

$8,017,377.95

Omaha, NE

 

 

Engineer's Opinion (HGM)

$805,757.00

$2,822,182.50

$645,737.00

$68,402.00

$55,000.00

$892,492.00

$328,895.36

$1,294,431.50

$6,912,897.36

 

 

The Contract Documents for the project include a special provision for incentives and disincentives.  If the maximum incentive of $225,000 is earned by Hawkins, the project cost will be $8,242,377.95.  Approval of the resolution accepting the bid includes authorization for this incentive payment.

 

Segment 3 of the reconstruction project will completely rebuild West Broadway from 28th Street to just west of 24th Street including the replacement of pavement, traffic signals, street lights, sidewalks, and storm sewers with drainage improvements as a major objective.  The project also includes streetscape amenities such as decorative pedestrian lights, brick paver bands behind the curbs and at intersections, ornamental fencing, ornamental arms for street lights, concrete pavers in crosswalks, decorative paving in the center turn lane and at key intersections, raised planted medians, neighborhood masonry columns, and trees.

 

As a condition of the Transfer of Jurisdiction, Iowa DOT has provided $20 million in funding for assuming ownership of the roadway previously identified as US-6.  This project is included in the FY19 CIP with a revised budget of $4,000,000 in IDOT funding, $1,765,000 from GO Bonds, and the balance in Sales Tax Funds.  The Iowa West Foundation has agreed to provide funding for the streetscape amenities, which are estimated to be $1,600,000.  

 

The project schedule is as follows: Award March 11, 2019
Construction Start April 2019 (weather dependent)
Substantial Completion February 14, 2020
Recommendation

Approval of this resolution.

 