Council Communication

Department: Public Works Admin
Case/Project No.: PW18-08
Submitted by: Matthew Cox, City EngineerĀ 
Resolution 19-12Council Action: 1/14/2019
Description

Resolution accepting the bid of Bluffs Paving and Utility Co. Inc. in the amount of $534,519.54 for the S. 6th Street Reconstruction.  Project #PW18-08

Background/Discussion

On December 20, 2018 bids were received in the office of the city clerk as follows:

Division I General

Division II Pavement

Division III Storm Sewer

Division IV San. Sewer

Total

Bluffs Paving and Utility Co. Inc., Crescent, IA

$98,369.47

$281,892.37

$68,070.30

$86,187.40

$534,519.54

Carley Construction, LLC, Council Bluffs, IA

$119,300.00

$293,989.25

$61,615.00

$117,166.00

$592,070.25

Valley Corporation, Valley, NE

$129,393.83

$408,390.93

$67,872.63

$130,688.26

$736,345.65

Engineer's Opinion (Olsson)

$93,180.00

$289,655.00

$64,682.00

$84,125.00

$531,642.00

 

Pottawattamie Arts, Culture & Entertainment (PACE) is a 501(c)3 organization with a mission to strengthen, develop and promote arts, cultural, and historical institutions, organizations, and activities in Council Bluffs and Pottawattamie County.  PACE is currently constructing a new arts and cultural center in the Harvester II building, located west of the Harvester I building on South Main Street.  The property for the new center is also bordered by S. 6th Street.

 

The City previously reconstructed S. 6th Street between 9th and 10th Avenues in 2012 in coordination with the new Community Health Center. 

 

Improvements are needed to replace the remaining sanitary sewer which dates back to the 1950’s and to improve the street now that the railroad tracks previously located along 11th Avenue have been removed.  This project will continue the needed reconstruction of 6th Street, south of 10th Avenue in coordination with the Harvester II/PACE project construction. 

 

This project was included in the FY18 CIP with a revised budget of $750,000 using $450,000 in GO Bond funding and the balance in Sales Tax Funds. 

 

The project schedule is as follows:    

                                                        Construction Start: Spring\Summer 2019

                                                        Construction End:  November 2019

 

 

                              

Recommendation

Approval of this resolution.

 