| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: BM19-03
Submitted by: Pat Miller, Public Works Operations Director | Resolution 19-08 | Council Action: 1/14/2019 |
|
| | | | | | | | Description
Resolution approving the plans, specifications, form of contract, and cost estimate for the Mid America Center Score Board Replacement Project. Project No. BM19-03 |
|
| | | | | | | | Background/Discussion
The existing scoreboards in the arena were installed when the Mid America Center was built in 2002. The failure rate and reliability of this scoreboard during events has escalated over the last few years. Replacement parts are becoming more expensive and difficult to obtain. Reliability has become a concern.
The new high resolution LED display board will captivate audiences. It will provide the guests with some of today’s most advanced video technology enhancing their overall experience. Advertising upcoming events will aid in marketing this venue.
The estimated cost of this project is $ 640,000. Funding for this project will be paid for by Capital Improvement Funds.
| The project schedule is as follows: |
Hold Public Hearing |
January 14, 2019 |
|
Bid Letting |
February 13, 2019 |
|
Award |
February 25, 2019 |
|
Construction End |
May 1, 2019 |
|
|
|
|
|
| | | | | | | | Recommendation
Approval of this resolution.
|
|
|