Item Coversheet

Council Communication

Department: Public Works Admin
Case/Project No.: BM18-04
Submitted by: Pat Miller, Public Works Operations Director 
Resolution 18-196Council Action: 6/25/2018
Description

Resolution accepting the work of Omni Engineering for the Bass Pro Shop Parking Lot Repair Project as complete and authorizing the Finance Director to issue the final payment and retainage in the amount of $5,485.49 in 30 days.

 

Background/Discussion

Bass Pro Shop was constructed in 2005.  There have been minimal repairs to the parking lot since that time.  There are many areas during the summer that have become tripping hazards. Water freezing in the same areas poses safety risks during the winter.

 

The entire parking lot also requires sealing of the entire surface and restriping which is normal maintenance of a lot that age.

 

Repairing the hazards and resealing and restriping the parking lot will ensure the parking lot will remain a safe environment.

 

A public hearing was held and the plans, specification and form of contract were approved by City Council on September 11, 2017 at 7:00 pm.  On January 23, 2018 at 10:00 am the City Clerk received bids for the Bass Pro Shop Roof Parking Lot Repair Project and on February 12, 2018, the City entered into a contract with Omni Engineering for the Bass Pro Shop Parking Lot Repair Project. 

 

Bid Submitted:

Omni Engineering - $105,443.20

 

Funding for this project will be paid for by the Iowa West Foundation.

 

Recommendation

Approval of this resolution.

 

ATTACHMENTS:
DescriptionTypeUpload Date
Resolution 18-196Resolution6/19/2018