Case/Project No.: Trolley Park Playground Improvements
Submitted by: Vincent Martorello 
Resolution 25-177
ITEM 4.A.
Council Action: 7/14/2025
Description

Resolution to authorize the Mayor to initiate the Trolley Park Playground Improvement, Project #2606, by issuing a bid for the project.

Background/Discussion

The City Council approved $261,000.00 for improvements to Trolley Park Playground Improvements in the FY 26 CIP.   The existing rubber safety surface is deteriorating and needs to be replaced.  The project scope also includes adding two stand-alone pieces of play equipment.  

 

The opinion of probable cost has been updated and the estimated for the project, including construction and design fees is $259,097.45 and is within the approved project budget.

 

Notice of Public Hearing was published as required by law, and a public hearing was held on July 14, 2025.

Recommendation

Approve resolution to authorize the Mayor initiate the Trolley Park Playground Improvement, Project #2606 , by issuing a bid for the project
ATTACHMENTS:
DescriptionTypeUpload Date
Resolution 25-177Resolution7/7/2025