Department: Public Works Admin
Case/Project No.: PW24-11
Submitted by: Matthew Cox, Public Works Director 
Resolution 25-130
ITEM 3.C.
Council Action: 5/19/2025
Description

Resolution accepting the work of Neuvirth Construction, Inc. as complete and authorizing the release of retainage after 30 days if no claims are filed in connection with the N. 28th Street Storm Sewer Rehab, Phase IV. Project #PW24-11

Background/Discussion

The N. 28th Street drainage basin limits are approximately I-29 to Avenue F and N. 10th Street to N. 33rd Street.  This area is roughly 580 acres.  The existing storm sewer network in this area was constructed in the 1950’s and is undersized causing frequent street flooding. The existing storm sewer interceptors are located along Avenue L, North 24th Street, and Avenue K.  In the past, high ground water conditions have caused several of the storm interceptors to fail, resulting in costly emergency repairs.

 

Phase IV included the replacement of the storm sewer interceptor in Avenue L from 2700 Avenue L to 28th Street. The project required the reconstruction of the roadways and sanitary sewer.  The phased approach of this rehabilitation project was based on prioritizing the roadways with existing storm sewer interceptors, frequent flooding areas, and infrastructure that is in poor condition needing immediate replacement.

 

The project was included in the FY24 CIP with funding from Local Option Sales Tax and Sewer Funds.

 

Division I Division II Division III Division IV Division V
General Pavement Storm Sewer Sanitary Sewer Water Main Total
Original Contract Amount $700,815.05 $633,051.06 $1,894,231.64 $498,690.75 $303,962.75 $4,030,751.25
Change Orders (-2.96%) ($15,073.89) ($55,793.78) ($16,019.46) ($17,050.99) ($15,260.27) ($119,198.39)
Final Contract Amount $685,741.16 $577,257.28 $1,878,212.18 $481,639.76 $288,702.48 $3,911,552.86
Less Previous Payments $651,454.10 $548,394.42 $1,784,301.57 $457,557.77 $274,267.36 $3,715,975.22
Retainage Due Contractor $34,287.06 $28,862.86 $93,910.61 $24,081.99 $14,435.12 $195,577.64

 

The Contractor received one non-compliance notice.

 

Recommendation

Approval of this resolution accepting the work of Neuvirth Construction, Inc. as complete and authorizing the release of retainage after 30 days.

 