| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: PW25-24
Submitted by: Matthew Cox, Public Works Director | Resolution 25-111
ITEM 4.A. | Council Action: 4/21/2025 |
|
| | | | | | | | Description
Resolution approving the plans and specifications in connection with the Kenmore Avenue Sanitary Sewer Reconstruction. Project # PW25-24 |
|
| | | | | | | | Background/Discussion
The sanitary sewer in Kenmore Avenue from 105 Kenmore to 134 Kenmore is failing and in need of replacement. It has been discovered that there are several sanitary sewer pipes in this street segment that are undersized and in poor condition. The existing pipes will be replaced with a single sewer main constructed with appropriate materials in the correct size, allowing all adjacent lots to be served.
This project was added to the FY25 CIP. The estimated cost of the project is $300,000, which includes engineering. Local Option Sales Tax funds will be used.
| The project schedule is as follows: |
Hold Public Hearing |
April 21, 2025 |
|
Bid Letting |
May 8, 2025 |
|
Award |
May 19, 2025 |
|
Construction Start |
June 2025 |
|
|
| | | | | | | | Recommendation
Approval of this resolution to hold the public hearing.
|
|
|