Background/Discussion
The City Council approved $155,000.00 for the Pirate Cove Improvement Project, R26-05. The project includes a concrete plaza and installing two shelters in an area formerly used as a sand volleyball court. Three bids were received for the project.
Dostals Construction Co. Inc. - $87,875.00
Western Iowa Utilities (Hildreth Landcape Inc) - $88,387.70
Judds Bros Construction Co - $97,535.00
Dostals Construction Co. Inc. is the apparent low bidder. The probable cost for the project, including, Dostals’s cost, remaining design fees, and the purchase of the two shelters is $151,193.75 and is within the approved budget of $155,000.00.
It is our goal to have the concrete installed before the pools open over Memorial Day weekend. The shelters will be installed in the fall after the pools close. This is due to the time it will take to receive the shelters once an order is placed.