Background/Discussion
The Entertainment District located between 23rd Avenue and I-80/29, and from 24th Street to 35th Street is a premier destination location within the City of Council Bluffs and includes the Mid-America Center. The parking lots that surround the Mid-America Center are owned by the City and the paving has degraded to the point where maintenance is difficult and there are safety concerns because of the poor condition.
A study was performed in 2011 and updated in 2015 which recommended the replacement of the parking lots. The conceptual plan suggested that the work could be performed in phases over a few years. The work has been programmed in multiple years of the CIP.
Four phases have been completed. Phase 1 included the lot south of the convention center and a portion of the west lot. Phase 2 included the lot just west of the south lot near the convention center. Phase 3 finished the west lot. Phase 4 included a portion of the north lot.
Phase 5 includes the northwest lot (see attached map).
This project was included in the FY25 CIP with a budget of $700,000 from G.O. Bonds and $300,000 from the General Fund.
| The project schedule is as follows: |
Set Public Hearing |
January 13, 2025 |
|
Hold Public Hearing |
January 27, 2025 |
|
Bid Letting |
February 20, 2025 |
|
Award |
March 10, 2025
|