| | | | | | | | Council Communication
Department: Public Works Admin
Case/Project No.: PW25-21
Submitted by: Matthew Cox, Public Works Director | Resolution 24-296
ITEM 6.C. | Council Action: 10/21/2024 |
|
| | | | | | | | Description
Resolution accepting the bid of Midwest DCM for the Council Bluffs Recycle Center Paving and Scale Foundation Removal. Project# PW25-21 |
|
| | | | | | | | Background/Discussion
On October 9, 2024 bids were received through the City bidding software Ion Wave as follows:
|
Midwest DCM, Omaha, NE |
|
$61,831.50 |
|
DPS, LLC, Omaha, NE |
|
$101,735.25 |
|
TK Concrete, Inc., Pella, IA |
|
$135,370.00 |
|
Engineer’s Estimate (HGM) |
|
$81,450.00 |
The outbound scale at the City’s Recycling Center was installed in 1997 and has been taken out of service, replaced by two new inbound and outbound scales.
This project will remove the old scale foundation, ramps, and deteriorating concrete in the area. The area where the old scale was located will be paved creating new traffic lanes for outbound non-scale traffic.
This paving project will finalize the improvements to the outbound traffic lanes, significantly enhancing traffic flow at the facility.
The cost for this project was included in the Recycling Center Operating Budget.
| The project schedule is as follows: |
Award |
October 21, 2024 |
|
Construction Start |
October 2024 |
|
|
| | | | | | | | Recommendation
Approval of this resolution to accept the bid of Midwest DCM. This project will create new traffic lanes for the Recycling Center outbound non-scale traffic.
|
|
|