Item Coversheet

Council Communication

Department: Public Works Admin
Case/Project No.: PW24-21A
Submitted by: Matthew Cox, Public Works Director 
Resolution 24-291
ITEM 4.B.
Council Action: 10/21/2024
Description

Resolution approving the plans and specifications for the Kanesville Sanitary Sewer Extension.  Project # PW24-21A

Background/Discussion

Future commercial developments near the I-80 Interchange at Kanesville Boulevard will require sanitary sewer improvements. 

 

The proposed sewer will tie into a sewer that is being constructed as part of project PW24-21.  The sewer will be constructed in the eastbound lanes of Highway 6 under the I-80 bridges from the west side of the interchange to the east side of the interchange and will serve the property in the northeast quadrant of the interchange.

 

The project was included in the FY24 CIP with ARPA identified as the funding source.  ARPA Revenue Loss funds have been authorized for the engineering and construction costs of the project.  The construction estimate for this phase is $1,400,000 including construction engineering.  

 

The project schedule is as follows: Hold Public Hearing October 21, 2024
Bid Letting November 7, 2024
Award November 18, 2024
Construction Start May 2025

 

Recommendation

Approval of this resolution to approve the plans and specifications. This project extends sanitary sewer to the east for future developments. 

 