Item Coversheet

Council Communication

Department: Public Works Admin
Case/Project No.: PW24-12
Submitted by: Matthew Cox, Public Works Director 
Resolution 24-294
ITEM 6.A.
Council Action: 10/21/2024
Description

Resolution accepting the bid of Compass Utility, LLC for the South 23rd Street Rehab, Phase I project.  Project # PW24-12

 

Background/Discussion

On October 3, 2024 bids were received through the City bidding software Ion Wave as follows:

 

Division I Division II Division III Division IV
General Pavement Storm Sewer San. Sewer Total
Compass Utility, LLC $174,845.35 $502,407.81 $139,165.31 $517,102.83 $1,333,521.30
    Council Bluffs, IA
Bluffs Paving and Utility Co. Inc. $208,968.95 $604,834.22 $177,966.24 $494,019.43 $1,485,788.84
    Crescent, IA
Vrana Construction $329,378.90 $551,246.07 $248,910.54 $659,935.35 $1,789,470.86
    Omaha, NE
Engineer's Opinion $239,420.50 $435,294.00 $169,331.00 $407,820.00 $1,251,865.50

 

The South 23rd Street sanitary sewer is a collector sewer receiving flow from the area between 20th Street and 26th Street and from I-29 south to 6th Avenue.  The trunk sewer is old, in poor condition, and needs to be replaced.

 

 The existing street has poor drainage and areas of the pavement and curbs are deteriorated. 

 

 The project will reconstruct South 23rd Street from 3rd Avenue to 6th Avenue. 

 

 This project was included in the FY24 CIP with a budget of $700,000 in Local Option Sales Tax funds and $300,000 in sewer funds. A revised total project budget of $1,500,000 is required to complete the project.

 

 The project schedule is as follows:     Construction Start       Spring 2025

 

 

Recommendation

Approval of this resolution to accept the bid of Compass Utility, LLC for the South 23rd Street Sewer Rehab, Phase I Project.

 

ATTACHMENTS:
DescriptionTypeUpload Date
Resolution 24-294Resolution10/16/2024