Background/Discussion
Future commercial developments near the I-80 Interchange at Kanesville Boulevard will require sanitary sewer improvements.
The proposed sewer will tie into a sewer that is being constructed as part of project PW24-21. The sewer will be constructed in the eastbound lanes of Highway 6 under the I-80 bridges from the west side of the interchange to the east side of the interchange and will serve the property in the northeast quadrant of the interchange.
The project was included in the FY24 CIP with ARPA identified as the funding source. ARPA Revenue Loss funds have been authorized for the engineering and construction costs of the project. The construction estimate for this phase is $1,400,000 including construction engineering.
| The project schedule is as follows: |
Set Public Hearing |
October 7, 2024 |
|
Hold Public Hearing |
October 21, 2024 |
|
Bid Letting |
November 7, 2024 |
|
Award |
November 18, 2024 |
|
Construction Start |
May 2025 |