Description

Resolution to approve Change Order #2 for the Valley View Dog Park adding $13,005.00 to the contract amount.  Project #R23-13
Background/Discussion

The dog park will consist of two fenced areas – one for large dogs and one for small dogs, concrete walkway, concrete central plaza, shade structures, dog waste stations, and drinking fountains for people and dogs.

 

Change Order #1 has been executed in the amount of $12,813.84 and included additional concrete walkway within the dog park as well as new curb and ADA compliant ramp at the entrance to the dog park.

 

During execution of the project, it was discovered that additional concrete walkway near the entrance to the dog park needs to be replaced to eliminate the existing trip hazards.  The replacement cost of this work is $13,005.00

 

This project includes a budget of $300,852.40 available for construction.  The revised contract amount will be $301,569.34, including C.O. #1 ($12,813.84) and C.O. #2 ($13,005.00).  Funds within the Park Maintenance operating budget have been identified to cover the $716.94 project budget deficit.  

Recommendation

Approval of this resolution.